UPDATE. Worthing
– Lancing A27.
Despite
all the announcements originally made by government that massive improvements
would take place, there is now considerable confusion over what will actually happen
long the Worthing - Lancing section of the A27 due to lack of funding.
The latest (15.09.2016) from a Highways
England (HE) presentation given to the A27 Working Group in Worthing is that
they are very early into the process for Worthing and Lancing and off the back
of work done in 2015, Government have now said that to improve the junctions
and capacity of the road, there would be a budget of between £50-100million.
The meeting was told that a lot of effort
had gone into gathering feedback from stakeholders, it was also told that purchasing
many properties was far out of budget so was not an option anymore. Meaning a
full dual carriage way between Lancing and Worthing is unlikely. That leaves
only the option to improve traffic signals and particularly the junctions.
Parsons Brinkerhoff (PB) the consultants are
now working on looking at designs and modelling so as to understand costs. The
consultation in public has now slipped to late spring/ early summer next year.
The meeting also heard from a local MP who
questioned why more money could not be found when £300million was found for the
Hindhead tunnel rather than the £70millon originally budgeted. That extra is half
the bill for turning A27 into dual carriageway between Lancing and Worthing he
said. Adding why can’t we find more money?
The MP continued that the accident rate along
the present alignment of the road is 4x higher than it should be, usually if
there are more than 12-15 thousand vehicle movements a day then a single
carriageway road is turned unto dual carriageway.
The meetings Chair added it is claimed
that a lot of it is local traffic rather than through traffic. Although a lot
of work has gone into gathering travel data, why are results still unavailable?
HE agreed to send the latest travel data
summary to the Chair within a couple of weeks to see how much is through
traffic rather than joining or leaving along the route.
HE
confirmed purchasing of houses is premature, as is discussion of numbers. That
process can’t start until the Secretary of State has confirmed the preferred
route. There are no preferred options at this
time, all options are under review and engineers are in the early design stage
for all options.
Other questions to HE were:
Are
you allowed to consider collaborative funding by councils etc?
HE
- yes, if there is money available it can be considered but would be needed
before doing design plans.
Question. WSCC contributed to the Chichester
work but are they contributing to Worthing/Lancing one?
HE - not that we are aware.
Question. - If there were options over indicated budget,
but would make considerable improvement, could you approach government about an
additional amount?
HE - Chichester funding comes from a developer
contribution due to large numbers of new houses – Our part of A27 does not have
this opportunity.
Question. - Getting rid of lights at Lyons
farm, roundabout would be better and help traffic through West Street in
Sompting.
HE – it is a key junction being looked at and
yes it would be.
Question. - Can you confirm that full Dualling
is not an option? Could be a big problem with property demolition and blight etc
HE- if we can come up with other cheaper
options then we may be able to do some Dualling. We cannot confirm for sure – it’s
too early in the process
Question. - Does full Dualling mean
national speed limit and also service roads etc?
HE - both have been practically ruled out
on costs, but government have asked us to consider them.
Question. - Is there set budgets for
certain areas, holistic approach?
HE - budgets for areas yes but amounts can
be moved if projects fail etc.
Question. - Has there been a price
comparison between Dualling and a northern bypass?
HE - junctions are our focus but that may
lead to full Dualling at some point. – There were some early concept level
costing that we can send to you.
Question. Is it better to take a Holistic
approach rather than talking about a large road we won’t actually get? What
about dealing with buses etc.
HE – We have spoken to rail etc. but it doesn’t
seem like any more services can be run due to capacity issues.
Question. Could we have the costings etc.
for the plans that were ruled out for Long Furlong improvements 1995/6?
HE – we will see if these are available.
The
Chair thanked HE for attending as they left after their session.